Direct materials $2,465 Direct labor-hours 73 labor-hours Direct labor wage rate $ 18 per labor-hour Machine-hours 135 machine-hours The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $19 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 593 would be:
Front

Advertisement

*DM = 2, 465 * DL = 73 X $18 =1314 * Machine hrs = 135 X $19 = 2565 --> 2,465 + 1314 + 2565 = $6344 total cost

About the flashcard:

This flashcard is meant to be used for studying, quizzing and learning new information. Many scouting web questions are common questions that are typically seen in the classroom, for homework or on quizzes and tests. Flashcards vary depending on the topic, questions and age group. The cards are meant to be seen as a digital flashcard as they appear double sided, or rather hide the answer giving you the opportunity to think about the question at hand and answer it in your head or on a sheet before revealing the correct answer to yourself or studying partner. Some questions will include multiple choice options to show you the options involved and other questions will just have the questions and corrects answers. Simply reveal the answer when you are ready to check your work. Absolutely no cheating is acceptable.